HS2 ‘unachievable’ according to major projects body

Posted

by

The HS2 programme has received an “unachievable” rating by the official infrastructure watchdog.

Credit: Aaron Chown/PA Wire

The Infrastructure and Projects Authority (IPA) gave a “red” rating to the plans for the construction of the first two phases of the rail line, from London to Birmingham and then on to Crewe in Cheshire.

The red rating, contained in the IPA’s annual report on major projects – which was released last week, states: “Successful delivery of the project appears to be unachievable.

Article continues below…
Advert

“There are major issues with project definition, schedule, budget, quality and/or benefits delivery, which at this stage do not appear to be manageable or resolvable.

“The project may need re-scoping and/or its overall viability reassessed.”

Earlier this month, HS2 Ltd’s chief executive Mark Thurston, 56, announced his resignation amid major delays and cost pressures for the high-speed railway project.

Article continues below…
Advert

He is to leave his role in September after six-and-a-half years leading the Government-owned company.

HS2 was initially scheduled to open in 2026, but this has been delayed to between 2029 and 2033 due to construction difficulties and rising costs.

A budget of £55.7 billion for the whole project was set in 2015, but the target cost excluding the eastern leg of Phase 2b from the West Midlands to the East Midlands has soared to between £53 billion and £61 billion at 2019 prices.

Article continues below…
Advert

In March, Transport Secretary Mark Harper announced work at Euston would be paused for two years as costs had ballooned to £4.8 billion compared with an initial budget of £2.6 billion.

Mr Thurston’s resignation announcement came while Phase One of the project between London and Birmingham is at peak construction, with major work taking place at more than 350 sites.

The IPA is the Government’s centre of expertise for infrastructure and major projects. It sits at the heart of government and reports to the Cabinet Office and HM Treasury.

Article continues below…
Advert

A Department for Transport spokesman said: “Spades are already in the ground on HS2, with 350 construction sites, over £20 billion invested to date and supporting over 28,500 jobs.

“We remain committed to delivering HS2 in the most cost-effective way for taxpayers.

“HS2 will bring transformational benefits for generations to come, improving connections and helping grow the economy.”

An HS2 Ltd spokeswoman said: “HS2 is now hitting peak construction, with work intensifying and huge civil engineering structures taking shape along Phase One of the route. Our priority is to maintain the fantastic momentum already underway to ensure the initial high speed services – connecting Old Oak Common and Birmingham Curzon Street – are operational by the current target of the early 2030s.”


Advert

Railway Reads

From the history of steam through to 21st century rail transport news, we have titles that cater for all rail enthusiasts. Covering diesels, modelling, steam and modern railways, check out our range of magazines and fantastic subscription offers.

Posted

in

,

Tags:

Latest Issue

Newsletter Signup